Just some observations.

If your field is called DATE, change the name. It will intefere with the Access function Date() in calculations and statements.

Even if there is more data besides date and date commencing in your table. You should not actually storing date commencing. You should be just recalculating it on the fly when you need it based on the date. You're storing extra data that's bloating your dB size.

The Sunday prior to any date is simply

Date Commencing = DateAdd("d", -1 * Weekday([YourDateField]) + 1, [YourDateField])


Greg Serrano